Site Status
I visited Balador Athena site on 7th of June to check the progress. I could see workers were working on the site. Mostly they were busy in painting the outer walls of the buildings. The coloring of 'F', 'G', and 'H' was almost complete. And few days of coloring work was remaining for the other buildings.
The club house related construction work was on. Also, they had laid the layer of stones for the internal roads. The site representative informed me that the next step is to lay the paving blocks on the internal roads.
Expected delivery date
As this is what we all are eagerly waiting for, I asked about the expected delivery date. She informed me that they are planning to handover the flats by end of October 2014.
Early possession
While talking with her, she informed me that they are also thinking of giving early possession to few flat owners on owners request, by sending an email to them. As they are planning to apply for part Occupation Certificate (OC).
I sent them an email and later when I inquired about the early possession status, they informed me that it would not be possible. The reason they gave me is, Talegaon Municipal council wants them to finish the remaining work first before granting them the OC.
Some pics of the site taken on 7th June 2014
If you have any updated information on Balador Athena and would like to share with me and others please use the comments section below. Also, if you have latest pics of the site, you can send me on my email id and I will post it on this blog.
I visited Balador Athena site on 7th of June to check the progress. I could see workers were working on the site. Mostly they were busy in painting the outer walls of the buildings. The coloring of 'F', 'G', and 'H' was almost complete. And few days of coloring work was remaining for the other buildings.
The club house related construction work was on. Also, they had laid the layer of stones for the internal roads. The site representative informed me that the next step is to lay the paving blocks on the internal roads.
Expected delivery date
As this is what we all are eagerly waiting for, I asked about the expected delivery date. She informed me that they are planning to handover the flats by end of October 2014.
Early possession
While talking with her, she informed me that they are also thinking of giving early possession to few flat owners on owners request, by sending an email to them. As they are planning to apply for part Occupation Certificate (OC).
I sent them an email and later when I inquired about the early possession status, they informed me that it would not be possible. The reason they gave me is, Talegaon Municipal council wants them to finish the remaining work first before granting them the OC.
Some pics of the site taken on 7th June 2014
Balador Athena: View of the open area and 'G', 'H' building |
Balador Athena: View of the open area and 'F', 'G' building |
Balador Athena: Club house |
Balador Athena: View of 'E' building |
Balador Athena: Internal road in front of 'D' building |